New Mixing Plant in Malaysia Built by BT-Wolfgang Binder

Tuesday, 31 March 2015

Large_new-mixing-plant-in-malaysia-built-by-bt-wolfgang-binder

GLEISDORF (AT) – Founded in Milan in 1937, MAPEI is one of the world leaders in the manufacturing of adhesives, sealing and chemical products for the building industry today. Currently, 70 subsidiary companies with 64 factories belong to the MAPEI group which is active in more than 31 countries on all five continents.

In November 2013, MAPEI awarded a contract for the construction of a new dry building material mixing plant to the Austrian general contractor BT-Wolfgang Binder GmbH. The order is worth some two million euros.

BT-Wolfgang Binder carries out the entire planning, construction, production and delivery of the machines, the silos and the steel structure, including the façade. The silos, the steel structure as

well as the tanks and containers were built in Malaysia according to the statics and shop drawings provided by the general contractor. The machines were packed for carriage overseas and dispatched in containers to Malaysia from Koper (Slovenia).

Chief erectors and a supervisor deployed by BT-Wolfgang Binder performed the assembly, assisted by Malaysian personnel. The concrete foundations and the electrical installations were provided by the customer. In mid-October 2014, the plant was successfully handed over and production in Nilai in central Malaysia could begin.

Thank to excellent collaboration between BT-Wolfgang Binder’s Project Department, the customer in Malaysia and the Engineering Department of MAPEI in Milan, supervised by Dr. Guido Trussardi and Project Manager Stefano Barsotti, the plant could be handed over and commissioned according to schedule despite the great distances. During hand-over MAPEI ordered another dry building material mixing plant for Australia at BT-Wolfgang Binder.

Technical data:

  • At full capacity, some 35 tons of adhesive and mortars can be manufactured in the new factory per hour.
  • The delivered raw materials such as cements, sands and binding agents are being stored in the following silos: four main component silos with a capacity of 60 m³ each as well as six main component silos with a capacity of 12 m³ each.
  • Dosing screws in hopper scales perform the dosing process whereas the dosing of additives is taken care of by small component scales. The plant includes six additive containers with a capacity of two m³ each and a fibre box. From the scales, the material is fed into the batch mixer which has a net capacity of 2,400 l.
  • From the batch mixer, the material is either fed into the 4-nozzle packing machine or delivered to a lorry loading facility with a loading capacity of 80 m³/h.